Beckenham High Street Improvements

Beckenham High Street phasing timetable

The works will be completed in 8 phases of improvements. Works are currently largely on programme.

The completed phases are:

Phase A  - the junction improvements including new paving, kerbs and road surfacing at High Street, Albermarle Road, Rectory Road and Southend Road.

Phase 1 - new paving and kerbs on the eastern side of the High Street between Albermarle Road and Thorntons Corner.

Phase 2 - new paving and kerbs on the western side of the High Street between Rectory Road and Thorntons Corner.

Phase 3 -  new paving, kerbing and parking bays completed between Thorntons Corner and Lidl.

Phase 4 - new paving and kerbing between the northern side of Thorntons Corner and The Drive.

Future phases

Phase 5 – Lidl to Village Way 01/05/18 to 19/06/18

Phase 6 – Village Way to the war memorial roundabout 20/06/18 to 24/07/18

Phase 7 – The Drive to the war memorial roundabout 25/07/18 to 07/09/18

Phase 8 – War memorial roundabout 01/05/18 to 22/07/18

Keep up to date with bus diversions at http://www.tfl.gov.uk/BusChanges

Phasing and timetable plan