The council recognises that there have been some delays to the original works programme, that was agreed in November 2022. These delays are predominantly as a result of an unsuccessful tender process, which concluded in January 2024, where unfortunately no tenders were received. Officers subsequently undertook further soft-market engagement to ascertain how to make the project more appealing to potential contractors, and amended the tender process based on feedback received.
The project has been split into two phases, with the first phase focusing on the detailed design of the bridge and associated arboricultural and survey work. The initial phase of design work for the replacement bridge at Kelsey Park is now complete. The latter part of this design work focused on finalising the technical details needed to safely reuse the existing bridge abutments, helping to keep the project within budget.
The additional design work has led to a slight delay in the original envisaged programme, but it has enabled the council to avoid the significant costs associated with constructing new abutments, without compromising the structural integrity of the bridge.
We are now moving into the next phase of the project. Land and Water, the contractor who successfully delivered desilting works at Kelsey Park that completed in March this year, has been appointed to both carry out the permanent works design, which will then be followed by the bridge construction. On-site works are scheduled to begin in Autumn 2025, with the construction phased to ensure minimal disruption to park visitors.
The council continues to work closely with the Environment Agency to secure the necessary Flood Risk Activity Permit. Once this permit is in place, the second phase of construction will commence.
It is currently anticipated that the works will be completed by early-2026, with park visitors and residents thanked for their ongoing support and patience as the council continues to move forward to renew the much-cherished bridge in Kelsey Park.